ANALYSIS OF TIME AND COST CONTROL OF SCHOOL BUILDING PROJECTS USING CPM METHOD (Case study: Petra 6 Sidoarjo junior high school building construction project) SIDOARJO - EAST JAVA

Prasetyo, Riyan (2021) ANALYSIS OF TIME AND COST CONTROL OF SCHOOL BUILDING PROJECTS USING CPM METHOD (Case study: Petra 6 Sidoarjo junior high school building construction project) SIDOARJO - EAST JAVA. Other thesis, Universitas Darul Ulum.

[img] Text (ABSTRACK)
S1 162322201063 ABSTRAC.pdf - Submitted Version
Available under License Creative Commons Attribution Non-commercial Share Alike.

Download (8kB)
[img] Text (BAB 1 INTRODUCTION)
S1 162322201063 BAB 1 INTRODUCTION.pdf

Download (462kB)
[img] Text (BIBLIOGRAFI)
S1 162322201063 BIBLIOGRAPHY.pdf

Download (462kB)
[img] Text (FULL TESIS)
S1 162322201063 FULL TESIS.pdf
Restricted to Repository staff only
Available under License Creative Commons Attribution Non-commercial Share Alike.

Download (3MB) | Request a copy

Abstract

Good time control is expected to assist the implementation of the project according to the planned time. Project delays for contractors will experience time and cost losses, because the contractor's expected profits will be reduced, or no profit will be made at all. The delay in the completion of project work will cause losses to the operating time of the project results, so that the use of the project is delayed or delayed. As in the construction project for the Petra 6 junior high school building, work delays occurred, causing losses on the part of the provider (contractor). Due to the large number of various building work items that must be done, from the construction service provider or contractor a good and neat construction management is needed so that the project being worked on can be completed according to the contract time stated in the contents of the project contract.
However, in the process of carrying out the work until the completion of the work there was a delay in the work. To find work items that cause work delays, the Critical Path Method is used. The aim is to find out how to apply CPM (Critical Path Method) in estimating the end time of project completion for each week.
This research project for the construction of the Petra 6 Junior High School building is more advanced (5 days with a total cost of Rp. 9,711,658,219.84).

Item Type: Thesis (Other)
Uncontrolled Keywords: Proyek konstruksi, Pengendalian waktu dan biaya, Critical Path Method.
Subjects: T Technology > TA Engineering (General). Civil engineering (General)
T Technology > TH Building construction
University Structure > Fakultas Teknik > Teknik Sipil
University Structure > Fakultas Teknik > Teknik Sipil
Divisions: Fakultas Teknik > Teknik Sipil
Depositing User: Yusuf Salbiyah
Date Deposited: 25 Oct 2021 02:06
Last Modified: 25 Oct 2021 02:06
URI: http://repository.undar.ac.id/id/eprint/1833